Anticipated start :
March 2008 |
• |
Anticipated completion:
July 2009 |
• |
Architect:
Hanbury Evans Wright Viattas |
• |
Contractor:
Rentenbach |
• |
Project cost:
$8.45 million, University revenue bonds
|
UVa-Wise residence halls have had greater than 100 percent occupancy for the past eight years. To serve our growing enrollment and to continue to welcome new students into our close-knit residential community, the College needs a new residence hall.
Therefore, coming on the heels of the recent completion of Culbertson Hall, the College's newest residence hall will feature 120 beds, study areas, a residence life director's apartment, recreational space and a classroom. The project will be located near the Lake, facing the future center for the arts.
October 2008 Status: The primary power duct bank was installed. Second floor concrete planks have been installed and masonry work is in progress. The first floor sanitary sewer rough-ins and the under-slab electrical circuits are in progress.
August 2008 Status: Foundations are 70 percent complete. The sanitary sewer has been relocated and is functioning. The mason is mobilizing.
March 2008 Status: The site fence and erosion control fencing was installed. Demolition began on house three.
February 2008 Status: Working with the Department of Conservation and Recreation to secure a soil and water erosion permit.
January 2008 Status: We have received the Army Corp of Engineers permit and are awaiting the Department of Conservation and Recreation’s soil and water erosion permit.
November 2007 Status: Demolition plans are being finalized for the planned January removal of houses three and four.
October 2007 Status: The Board of Visitors approved the schematic drawings.
September 2007 Status: Value Management has been completed.
July 2007 Status: Design and pricing work continues on this project. Value Management will occur Aug. 14-15. June 2007 Status: Design and pricing continues on this project.
May 2007 Status:
Rentenbach of Knoxville, Tenn., has been selected as the Construction Manger at Risk for this project. At this time they are working with U.Va. Facilities Planning and Construction, UVa-Wise and Hanbury Evans Wright Vlattas to obtain an accurate estimate of the construction cost based on the design.
April 2007 Status: This project is proceeding with Schematic Design. Value engineering is currently being scheduled for early June. Interviews for Construction Management at Risk will take place on May 3. This project will be completed in conjunction with the Dining Hall to minimize congestion in the work zone.
|